The functions of Apex committee are:

  • Baseline mapping of existing FHTCs
  • Identify villages to be taken up under JJM
  • Assigning of ISA, PHED/ RWS Department official to villages
  • Workshops for ISAs on JJM implementation
  • Community familiarization with the objectives of JJM through IEC campaigns in coordination with PHED/ RWS Department
  • GP resolution for taking up JJM in village Constitution of sub-committee of Gram Panchayat, i.e. VWSC/Paani Samiti/ User Group, etc.
  • Undertake PRA activities
  • Capacity building of Gram Panchayat and/ or its sub-committee, i.e. VWSC/ Paani Samiti/ User Group, etc. functionaries.
  • Preparation of VAP
  • Approval of VAP
  • Preparation & finalization of design and estimates and technical approval as per existing departmental procedures.
  • Administrative approval of estimates
  • Determination of community contribution and its deposition in the bank account Obtaining necessary statutory clearances.
  • Testing for yield and quality Development/ augment of source Creation of infrastructure for water supply till
  • FHTC including source sustainability Entry into MB and preparation of running bills Greywater management works (to be executed in parallel with above)
  • 16. Enabling payment post 3rd party inspection Geo-tagging of assets Create and maintain register for accounts.